A storm and lightning strike on Monday caused a 10 MVA power transformer at the Aditmari-2 Sub-station (Hajiganj) to fail. This incident has left approximately 22,000 customers (roughly 50,000 people) across six unions in Aditmari and Kaliganj upazilas without electricity for four days. The outage has disrupted daily life, water supplies, and businesses, with replacement work currently underway.
| Scope | Source wording |
|---|---|
| 2 · upazilla | আদিতমারী ও কালীগঞ্জ উপজেলা |
District or Upazila level government authorities
Coordinating with the power department to ensure rapid restoration.
Other response agencies
A new transformer has been brought from Dhaka and replacement work is currently underway.